A call sheet template will carry you through day one. Not day two.

A call sheet is the official summons for a day of production: who reports, where, at what time, and what gets shot. It is the one document the whole unit actually reads, and the only one that commits the production to an hour. Looking for a template is the right instinct — it tells you which sections exist, in an order any 1st AD will recognise, so you are not inventing a structure the night before the first day.

What a template cannot do is survive contact with a schedule. It is ideal on day one and becomes a liability on day two, when weather flips two locations, an actor's availability moves and three versions of the same PDF are sitting in forty inboxes. This page covers both halves of that: the full anatomy of a call sheet, section by section, and the exact point at which retyping a template costs more than generating it from the shooting schedule.

  • Every section of a call sheet, and where each field actually comes from
  • What is genuinely typed versus what is copied out of the breakdown and the schedule
  • The logistics lines nobody asks for until the morning they are missing
  • Turnaround between wrap and the next call: the rule a template can never check
  • Word, spreadsheet or generated: what each option costs after a schedule change
  • Why the real problem with a call sheet is never layout — it is versions
Hands marking up a printed schedule with a pen on a desk beside a computer keyboard
A template is filled in by hand, day after day — which is exactly what makes it useful on day one and expensive from day two.

What a call sheet commits you to, and why structure matters

A call sheet does not inform, it summons. It is the document of record for each person's call time, for the rendezvous point and for the order of the day's scenes. Its job is to make a day executable without anyone having to phone the production office to check a detail — and that is the only standard by which a template should be judged. A missing section does not produce a less attractive document, it produces one phone call at six in the morning and then ten more. This is why call sheet structure is remarkably stable across productions, from a two-day short to a feature: it is not a presentation choice, it is the list of questions a crew asks before leaving home.

What a call sheet template contains, and where each field comes from

The first thing you notice filling in a template is how little of it is actually writing. Nearly everything is copied from documents that already exist. Unit call and estimated wrap come from the shooting schedule; the location, interior or exterior, day or night, and the background count come from the screenplay breakdown; cast calls come from crossing the two. Only production notes are genuine authorship. The table below sets out the full structure and marks, for each section, whether it is typed or copied — that column, more than the list itself, explains why writing call sheets by hand is such tiring work.

Call sheet structure and the source of each section
SectionActually typedSource document
Header: title, day number, date, production companyProject record
Key contacts: production office, 1st AD, location managerCrew list
Unit call and estimated wrapShooting schedule
Location, address and rendezvous pointRecce and shooting schedule
Scenes to shoot (number, INT/EXT, day/night, synopsis)Screenplay breakdown
Cast called, roles, makeup and on-set timesCasting and day-out-of-days
Background artists: numbers, call, wardrobe notesScreenplay breakdown
Crew called, department by departmentCrew list and shooting schedule
Technical requirements: grip, lighting, effects, vehiclesScreenplay breakdown
Meal break: time, place, head countPartlyCatering and people called
Access, parking and unit baseTyped by the location team
Weather, sunrise and sunsetPartlyDate and location of the day
Safety notes and nearest hospitalTyped by production
Production notes and a word from the directorTyped by production
Advance schedule: what shoots tomorrowShooting schedule

The header: who called the day, and who to ring when it goes wrong

The header looks decorative and never is. It carries the project title, the day number against the total — "day 7 of 23" situates a delay better than a date does — the date, the production company and, above all, the numbers that are answered on the day. Three are enough and all three must be there: production office, 1st AD and the location or unit manager. The classic failure is reusing the header of a downloaded template without replacing the contacts with the ones on duty: on a production where the location team rotates, the number printed last week reaches someone who is no longer on the unit. A call sheet is read on a phone, standing up, in the dark. The contacts belong at the top, not in an appendix.

Call times are plural, and most templates only have one box

This is the section a call sheet commits to most, and the one templates get wrong most often, because they usually offer a single "call time" field. A shooting day has several. There is the unit call for crew, cast calls staggered by makeup and wardrobe, a separate background call, first shot, the meal break and estimated wrap. Collapsing unit call into first shot brings cast in an hour early or crew an hour late, and nobody notices until the morning. A template with one time column forces you to invent a reading convention that only you know; pick one that separates calls by group explicitly, and state on the sheet which time is the crew call.

The day's scenes, in shooting order

The scene list is not script order: it is shooting order, decided by the schedule to group locations, effects and cast availability. Each line carries the scene number, interior or exterior, day or night, the set, a one-line synopsis, the characters present, the background count and — depending on the production — the page count in eighths. That last figure deserves attention: it is the only number that lets you say at wrap whether the day did what it promised. A template that omits it produces perfectly legible sheets and makes progress tracking impossible. You know which scenes remain; you never know how many days they represent.

Who is called: cast, background, crew

Three lists, three different logics. Cast are called individually, with a per-day status — working, hold, travel, rest — and that grid by role and by day is what contracts and payroll are built from. Background artists are called as a group, with their own time and wardrobe instructions. Crew are called by department, and the head count only varies occasionally: an extra grip for a dolly day, a second sparks for a night. The common failing of generic templates is melting all three into one list of names. You then lose the most useful piece of information on the page — the reason each person is there that day — and the 1st AD reconstructs it from memory.

The logistics lines nobody asks for until they are missing

These are the fields no template fills for you, and that nobody chases until the morning they are absent. The exact rendezvous address, which is not always the set address. Parking: where unit vehicles go, where everyone else goes, and under what permit. The unit base, dressing rooms and catering. Meal time, place and head count. Sunrise and sunset, which govern an exterior day far more reliably than the forecast does. The safety notes specific to the location, and the address of the nearest hospital. Finally the advance schedule — one line on what shoots tomorrow — which stops the crew from organising their lives around a rumour.

Turnaround: the rule a standalone template can never check

A template will accept any call time you type, including one that leaves too little rest after a late wrap. Yet turnaround — the gap between wrap and the next day's call — is the single most structuring constraint on a schedule, and the one that triggers penalty payments and fatigue arguments in equal measure. The point here is methodological rather than legal: the rule is verified between the estimated wrap of one day and the call of the next, which means between two call sheets, never inside one. A standalone document cannot check it by construction. If you work from a template, run that check separately on the schedule before you distribute anything, and remember that minimum rest periods are set by local labour law and by whichever union or collective agreement applies to your production.

The real problem with a template is not layout, it is versions

On a shoot, a call sheet is almost never written once. A location moves, weather flips two days, an actor's availability shifts: tomorrow's sheet changes, and sometimes next week's too. The risk is not presenting the document badly, it is a grip arriving at the time printed on the previous version. That is where a template reaches its limit, and it is not a question of how good the template is: a file attached to an email has no way to update itself, and a crew of forty has no way to tell which of three attachments is current. The only remedy, template in hand, is procedural — number the versions, stamp the time of issue, and reissue the whole document rather than sending a correction.

Film crew gathered around a camera on an outdoor location, with a clapperboard and actors in position
This is where a call sheet is actually judged: everyone in the right place at the right time, with nobody having had to call the production office.

Word, spreadsheet or generated from the schedule

Three ways of producing call sheets coexist, and they do not differ in output — all three print something legible. They differ in what happens after a change. A Word template is free and flexible, but every schedule change is retyped by hand. A spreadsheet adds arithmetic and dropdowns, at the cost of a layout that breaks the first time you export to PDF. Generating from the shooting schedule removes the retyping entirely, because the scheduled day and the call sheet are the same object seen from two sides. Disclosure: Soldum publishes one of the solutions described here, and this page.

Three ways to produce the call sheets for a shoot
MethodFreeNo content retypingRegenerates after a schedule changeDistribution and confirmations tracked
Word template
SpreadsheetPartly
Scheduling software with PDF exportDepends on the toolDepends on the tool
Soldum (breakdown, schedule and call sheets linked)7-day trial

When to move from a template to generation

There is no universal threshold, but there is a symptom. As long as you are writing one call sheet a day on a three-day shoot, the template wins: it costs nothing and you control it. The switch happens when you catch yourself copying the same fact for the third time — once into the breakdown, once into the schedule, once onto the sheet — or when you spend longer confirming that the crew is reading the right version than preparing the day itself. In Soldum the call sheet is not a separate module: it is the output of a day in the shooting schedule, which is itself derived from the AI breakdown of the screenplay. You do not make call sheets, you approve the schedule and they exist; every change produces a new time-stamped version, and the link already sent to the crew always shows the latest one.

What a template still gets right

Worth ending here, because it is what gets lost in the move to a tool: a call sheet template encodes real craft knowledge. The order of the sections is not arbitrary, nor is the separation of calls by group, and putting the contacts at the top of page one comes from dozens of shoots where they were somewhere else. Good software does not replace that structure, it adopts it and stops asking you to retype it. It is also why an incomplete document does not become complete by being generated: if the breakdown does not know a scene's location, or casting does not say which actor plays which sequence, the sheet comes out hollow whatever produces it. The question to ask a template and a tool is the same one: where do the fields come from.

What's your pre-production challenge?

What kind of project are you preparing?
What takes you the most time today?
How do you work right now?

Frequently asked questions

What should a call sheet contain?

+

The project header with the date and day number, the contacts answered on the day, call times by group, the location and its address, the scenes in shooting order, cast and background called, crew by department, technical requirements, the meal break, access and safety information, and an advance schedule for the next day.

Where can I find a free call sheet template?

+

Word and spreadsheet templates circulate freely between productions, and the structure they share is stable from shoot to shoot. The table on this page gives the full list, section by section: it is enough to build your own template, or to check that one you found elsewhere leaves nothing out.

What is the difference between a call sheet and a shooting schedule?

+

The shooting schedule covers the whole production: it distributes scenes across days in an order that groups locations and respects cast availability. The call sheet is the view of one of those days, issued to the crew as a summons. One is the production's planning tool, the other is the crew's document.

Who writes the call sheet?

+

The 1st AD is responsible for it on most productions, usually with the 2nd AD doing the data entry and the location department supplying the logistics. Production approves it before it goes out, since it commits the production to call times.

When should a call sheet be distributed?

+

The evening before is the convention, for a practical reason: everyone needs to plan travel and rest once the previous day has wrapped. A call sheet issued on the morning itself is not read by the people who have already left home.

How do you handle changes after a call sheet has gone out?

+

With a template, the only reliable method is procedural: number the versions, stamp the time of issue and reissue the whole document rather than a correction. With a linked chain, the schedule recalculates and the affected days reissue as a new time-stamped version on the same link, with no second document to send.

Do I need software to produce call sheets?

+

Not on a shoot of a few days: a well-structured template costs nothing and does the job. A tool starts to pay when the schedule moves often, when the unit passes a dozen people, or when you are copying the same information out of the breakdown for the third time.

Related reading

Informational page. Minimum rest periods, turnaround rules and working-time limits on a shoot are set by local labour law and by whichever union or collective agreement applies to the production, and they change. Check the rules in force with the relevant authorities and your own advisers before issuing call times. Soldum publishes one of the solutions described.